4 China firms, RP contractor linked to RP loan deferred by World Bank
Philippine Center for Investigative Journalism
Four Chinese companies and a Filipino firm were involved in the controversial multi-million roads project rejected by the World Bank, according to an official document obtained by the Philippine Center for Investigative Journalism. The road projects, which were originally packaged into two and were later split into three, underwent three successive rounds of bidding but were later rejected because of “strong signs of collusion and excessive pricing," a World Bank official said. All three projects, about $33 million-worth, have not pushed through. The World Bank did not state which companies were under investigation but the Asian Wall Street Journal reported that China State Construction Engineering Corp., after winning a $5.6-million contract in 2002, “tried to rig bids with a cartel of construction firms in two other road contracts, valued at $33 million." In its investigation, the fraud unit of the bank reportedly concluded that China State was involved in bid-rigging, although the East Asia department asked the board to approve the second phase of the National Roads Implementation and Management Program (NRIMP), which was worth $232 million. The World Bank recently decided to defer the implementation of NRIMP-Phase 2 following the procurement problems raised, until after “corruption issues" in the first phase have been resolved. Involved in bidding Based on information obtained from a senior government source, the construction firms involved in the failed biddings under the NRIMP-1 were: China State Construction Engineering Corp., China Road & Bridge Corp., China Geo-engineering Corp., China Wu Yi Co. Ltd, and E.C. De Luna Construction Corp. The first bidding, which was conducted in 2002, involved a P967.01-million approved budget for the contract (ABC) in Surigao del Sur and a P917.43-million contract in Negros Occidental and Oriental. The lowest bidders were China Road, E.C. Luna, and China State Construction. (See table below) The same companies were the lowest bidders in the second round of bidding in 2004, although the prices were already significantly different compared to 2002. The ABC for the Surigao road project was reduced to P901.66 million while the Negros project increased to over P1 billion. By 2006, when the third round was done, the projects were already split into three packages — the Surigao contract went up to P1.7 billion and the two other Negros Oriental/Occidental projects were worth P682.40 million and P640.57 million. China State was no longer among the lowest bidders, which were China Geo-Engineering, China Road, and China Wu Yi.
PROJECTS REJECTED BY WORLD BANK UNDER THE NRIMP PHASE I | ||
NAME OF PROJECT | COST - ABC | LOWEST BIDDER |
1st bidding, 2002 (under Secretary Simeon Datumanong) | ||
Surigao-Davao-Costal Road, Marihatag-Baroto & Tagbina-Hinatuan Section, Surigao del Sur | 967.01 | China Road |
Rehabilitation of Kabankalan-Basay/San Enrique-Vallehermoso Road, La Castellana-Canlaon Section | 917.43 | ECLuna/China State |
2nd bidding, 2004 (under Secretary Florante Soriquez) | ||
Surigao-Davao-Costal Road, Marihatag-Baroto & Tagbina-Hinatuan Section, Surigao del Sur | 901.66 | China Road |
Rehabilitation of Kabankalan-Basay/San Enrique-Vallehermoso Road, La Castellana-Canlaon Section | 1,013.53 | ECLuna/China Road |
3rd bidding, 2006 (under Sec. Hermogenes Ebdane) | ||
Surigao-Davao-Costal Road, Marihatag-Baroto & Tagbina-Hinatuan Section, Surigao del Sur | 1,170.59 | China Geo |
San Enrique-Vallehermoso Road, La Castellana-Canlaon Section, Negros Occidental/Oriental | 682.40 | China Road |
Kabankalan-Basay Road, Hinobaan-Basay Section, Negros Occidental/Oriental | 640.57 | China Wu Yi |